Question 1
The plumbing rough-in is complete in a framed commercial tenant space, but the rough inspection and prescribed tests have not occurred. The drywall crew is ready to close the walls. What should the plumbing contractor do next?
Show answer & explanation
Correct answer: C - Delay concealment until the rough inspection and required tests are approved